Gull Point Lodge Renovation

 

Beed's Lake Beach House


Architect: Thierry Amice, Facilities Engineer
Architect: Thierry Amice, Facilities Engineer
Inspector: Richard Wilson Inspector: Mel Pacovsky
Contractor: Vieco Development & Construction Inc. Contractor: Vieco Development & Construction, Inc.
Total Price: $1,052,744.00 Total Price: $281,785.00
Date Completed: 2/23/1999 Date Completed:  7/21/1997
   
 
 
Brushy Creek Dam

 

Designer:
Inspector: Larry Taylor
Contractor: Giese Construction & Woodruff Construction
Total Price: $7,606,363.60
Date Completed: 3/3/1998
 
 
 
Home Staff personnel Projects Iowa DNR Homepage
 
 

return to top

 

©2002 Engineering & Realty Services Bureau

Division of Administration

Iowa Department of Natural Resources

Wallace State Office Building

Des Moines, Iowa 50319

 

 

Webmaster: Don Labate